7 weeks prior
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
|
Full demo of new code and sign-off
|
Lead Developer
|
6 weeks prior
5 weeks prior
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
|
Announce code-freeze
|
Development manager
|
2.
|
✓
|
|
Once the integration server has ended with Monday's job Move awaiting issues to current integration it will be disabled and, issues will be manually picked for integration until the post-release "On Sync" period ends (usually 3 weeks after release).
|
Integration Lead
|
3.
|
✓
|
|
Prepare a fresh installation of the QA site based on the beta code to make sure the site is not affected by incremental upgrade steps during the development cycle.
|
QA Master Site Maintainer
|
4.
|
✓
|
|
Write documentation on new features in the dev docs, adding a link to it from the tracker issue, together with the label docs_required. The documentation will then be transferred to the new en version wiki when it is set up (3 weeks prior) and polished, with screenshots added.
|
|
4 weeks prior
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
|
Start working on the release notes (template) of the upcoming version.
|
Development Manager
|
2.
|
✓
|
|
Release normal weeklies but with these changes in the master branch:
- version.php: Move to $maturity = MATURITY_BETA and $release = 'X.Ybeta (Build:xxxxxxxx)'
- tag git repo with: "vX.Y.0-beta" (and MOODLE_XY_BETA as description and CVS tag)
And make packages available under download.moodle.org (and windows). Promote master up in the download page and adjust info for it.
|
Integration Lead
|
3.
|
✓
|
|
(Optionally) Announce Beta release in forums (ideally once packages are available).
|
Integration Lead
|
4.
|
✓
|
|
During the QA weeks integration becomes continuous; release STABLE weeklies normally but master release as often as possible (or on demand).
|
Integration Lead
|
5.
|
✓
|
|
At some points produce release candidates (Z = 1, 2, 3..), which are normal builds with:
- version.php: Move to $maturity = MATURITY_RC and $release = 'X.YrcZ (Build:xxxxxxxx)'
- tag git repo with: "vX.Y.0-rcZ" (and MOODLE_XY_RCZ as description and CVS tag)
- Make packages available under download.moodle.org (and Windows).
|
Integration Lead
|
6.
|
✓
|
|
Add a new version in the Plugins Directory with the version's name and the beta release version build number (https://moodle.org/plugins/admin/softwareversions.php).
|
Plugins Directory Maintainer
|
7.
|
✓
|
|
Tidy up current latest en version of Moodle Docs prior to copying it to create new version wiki as described in New docs version process.
|
Community Manager
|
8.
|
✓
|
|
Create new QA test cycle and invite community volunteers to start QA testing.
|
Community Manager
|
9.
|
✓
|
|
Update the QA testing dashboard.
|
Development Manager
|
10.
|
✓
|
|
Monitor QA fails. Check each fail is real and if so ensure an MDL issue has been created and correctly linked and labelled.
|
Testing Maintainer
|
11.
|
✓
|
|
Monitor MDL issues created for QA fails. Add them to the "Must fix for X.Y" list and get a developer to work on the issue immediately.
|
Development Manager
|
3 weeks prior
2 weeks prior
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
|
- Prompt developers to complete remaining QA tests.
- Ensure all QA tests are completed and passed by the end of the week.
|
Development Manager
|
1 week prior
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
|
Clone as many filters as needed in the Tracker, modifying them to point to the new, upcoming, branch (keeping same perms, title...).
|
Integration Lead
|
2.
|
✓
|
✓
|
Create new minor version X.Y.Z+1 in the Tracker (MDL and CONTRIB). Archive any version > 6 months old.
|
Integration Lead
|
3.
|
✓
|
|
Clone MDL-45486 and bump all versions, requires and dependencies along all plugins in codebase to planned release date.
|
Integration Lead
|
4.
|
✓
|
✓
|
Post a "Heads-up" message on the Partners forum and General Developer forum.
|
Development Manager
|
5.
|
✓
|
✓
|
Post a "Heads-up" message on Twitter and other outlets.
|
Digital Marketing Specialist
|
6.
|
✓
|
✓
|
Merge fixes from en_fix pack and then integrate them.
|
AMOS Maintainer
|
7.
|
✓
|
|
In https://github.com/moodlehq/moodle-behat-extension project:
- For the new stable version:
- Create a MOODLE_XY_STABLE branch from master
- Hardcode upstream projects versions in moodle-behat-extension/composer.json according to the latest pulled versions when installing/updating the dependencies to avoid upstream changes breaking stable branches tests
- Add a 1.XY.n tag to point to this new branch last commit
- Clone https://tracker.moodle.org/browse/MDL-43050 pointing to the tag created above and send it to integration
- For master:
- Add a 1.X(Y+1).0 tag for the new release in the master branch
- Clone MDL-39489, implement, and send it to integration (integration_held label).
|
Testing Maintainer
|
8.
|
✓
|
✓
|
Identify security issues that need to be integrated using the security_held label.
- Integrate from provided patches into supported branches (including branches supported only for security issues).
- Ensure security issues are given priority in weekly integration and testing.
|
Integration Lead
|
9.
|
✓
|
✓
|
Collect security issues into a clone of MDL-39530 to prepare for release of Security Advisories.
- Determine which security issues will be integrated.
- Request CVE Identifiers by emailing issue descriptions to distros@vs.openwall.org with a message like... The following security issues have been discovered in Moodle. We request CVE Identifiers for these issues. We will be releasing the security announcements for these on moodle.org on XXX at 12noon AWST which is 04:00 UTC. The email subject should include the characters [vs]. The format needs to be plain text or encrypted. When granted CVE Identifiers, our issues should appear in the CVE list. More instructions are available.
- Post security issues as a reply to the "Heads-up" message on the Partners forum.
|
Development Manager
|
10.
|
✓
|
✓
|
Review and complete the release notes for the upcoming minor versions.
- Ensure all issues labelled with "ui_change" or "api_change" are listed as functional or API changes respectively in the release notes.
|
Development Manager
|
11.
|
✓
|
|
Check on the "Must fix for X.Y version". Filter out unrealistic issues.
|
Development Manager
|
12.
|
✓
|
✓
|
Upgrade moodle.org and all other Moodle community sites (test sites first, then production) - Friday before release if not before
|
|
Releasing
Packaging
This should happen immediately before the next integration cycle begins on Monday (i.e., some days after last weekly, 2 days prior to official release).
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
✓
|
Make sure there are no real blockers introduced in the last weekly (install / upgrade ...). Confirm that the latest en_fix changeshave been generated and integrated.
|
Integration Lead
|
2.
|
✓
|
✓
|
Verify all unit tests and integration tests have passed.
|
Integration Lead
|
3.
|
✓
|
|
Verify QA tests have passed.
|
Integration Lead
|
4.
|
✓
|
✓
|
For major releases only:
- Update the CI server(s) by cloning all the "master" jobs to a new "MXY" view. Adjust "master" compare DB jobs to check for upgrade from MOODLE_XY_STABLE. Don't forget to re-chain the jobs properly.
Follow the "mdlrelease" steps:
- Run the prerelease.sh script to generate the target minor (--type minor) and major (--type major) releases and their corresponding tags. Follow the on-screen instructions. Triple verify all changes are correct!
- Push changes to integration.git (but tags)
- Once CI servers have ended and all jobs have passed, push tags and run the release.sh script to apply the changes to moodle.git
|
Integration Lead
|
5.
|
✓
|
✓
|
Post a "git repos updated & tagged" message on the Partner forum
|
Integration Lead
|
6.
|
✓
|
|
Create a new MOODLE_XY+1_STABLE branch in https://github.com/moodlehq/moodle-performance-comparison and set the new release commit hash as $basecommit
|
Testing Maintainer
|
7.
|
✓
|
✓
|
Wait for the automated moodle-package to finish building for all versions. Verify the process has ended successfuly (email).
For major releases only:
- Use the prerelease.sh script (--type back-to-dev) to move master to next X.Y+1 development version/branch. And push changes to integration.git - note this will lead to the "versions checker" failing for master, no problem, it will be fixed by the 1st cloned issue at #12 below).
|
Integration Lead
|
8.
|
✓
|
|
- Create new windows packager script (cloning the current master one and configuring it).
- Create new windows_wpiXY dir by cloning the previous one (HEAD based), configuring build-latest-XY.sh.
- Edit the stats.php script (in the serverscripts repository), adding the new branch to the versions. It will be automatically deployed.
|
Integration Lead
|
9.
|
✓
|
✓
|
In the Tracker...
- Visit the versions page and make the release, bumping all remaining open bugs to the next point release. This must be done both for the Moodle Project and the Add-ons project. Archive any version > 6 months old.
- Remove from all screens the custom fields belonging to 100% unsupported branches.
|
Integration Lead
|
10.
|
✓
|
|
Create the new "Pull X.Y Branch" and "Pull X.Y Diff URL" custom fields and spread them to all the screens needing them (copy from previous ones). Order them properly on each screen. Reindex Tracker.
Also, in the CI servers (1, 2), edit the "Bulk precheck issues" job to make it meet the new "Pull X.Y Branch" field created.
|
Integration Lead
|
11.
|
✓
|
|
Create the new "X.Y regressions" version to be applied to every issue found to be a recent problem introduced by the major release. These issues should get priority after release.
|
Integration Lead
|
12.
|
✓
|
|
Clone MDL-45502, MDL-45503 and MDL-45504, to be resolved ASAP.
|
Integration Lead
|
13.
|
✓
|
✓
|
Add/update the release date, build number and link on the Releases page and date in new version pages.
|
Integration Lead
|
Release day
Usually on Monday
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
✓
|
The execution of "moodle-package-extract-and-postprocess X" script may be needed if the releases *are not going to be published on Monday* but another weekday (X is the weekday, (1-7) starting in Monday). By default it happens automatically around 09:00 AM Perth/Australia time.
|
Integration Lead
|
2.
|
✓
|
✓
|
Verify release status, download pages and windows packages.
|
Integration Lead
|
3.
|
✓
|
✓
|
If needed, modify the downloads cfg script (serverscripts) to decide about branches status, master visibility and windows availability. Push changes, will be autodeployed in a few minutes.
|
Integration Lead
|
4.
|
✓
|
✓
|
Notify all registered sys admins, including security notes with CVE identifiers, using the mailing list server.
|
Development Manager
|
5.
|
✓
|
|
Post about the Major release on the moodle.org News forum
|
Lead Developer
|
6.
|
|
✓
|
Post about minor releases on the moodle.org News forum
|
Development Manager
|
7.
|
✓
|
✓
|
Post about the release on Twitter and other outlets. Update no. of releases on moodle.com 'Fact Sheet' page: http://moodle.com/news/moodle-fact-sheet/
|
Digital Marketing Specialist
|
8.
|
✓
|
|
New "X.Y+1dev" branch to be created in AMOS, to have master changes performed there. New install_XY_STABLE processing set up. These needs to be done anytime during the on-sync period.
|
AMOS Maintainer
|
9.
|
✓
|
✓
|
Verify, 24h after tagging, that https://moodle.org/dev/ has been updated with new versions. If not, file an urgent mdlsite issue, crons must be running!
|
Integration Lead
|
10.
|
✓
|
|
For en and de Moodle Docs, update default redirects and enable email notifications.
|
Moodle Docs Maintainer
|
11.
|
✓
|
|
Go through all points listed under Day of release in New docs version process.
|
Community Manager
|
12.
|
✓
|
|
- Decide the "Full demo", "Code freeze" and "QA begins" dates for the next X.(Y+1) major release and put them in the Moodle development calendar. They will be -7w, -5w and -4w before release date respectively.
- Update the "Full demo", "Code freeze", "QA begins" and Release dates on the Roadmap page.
- Add events to the HQ calendar for next Major release 6-months cycle according to the cycle plan: ~4 weeks planning and regression fixing, 2 sprints, 1 personal project week, 2 sprints, 1 personal project week, 1 sprint (which should lead up to code freeze).
- Notify the Community Manager of new dates to be added to the moodle.org calendar.
|
Development Manager
|
13.
|
✓
|
✓
|
Upgrade all moodle.org and moodle.net sites to latest release version.
|
System Administrator
|
14.
|
✓
|
|
Add calendar events in the moodle.org calendar for coming Major and Minor releases up to the next Major release.
|
Community Manager
|
1 week after
3 weeks after
1 month after
#
|
Major
|
Minor
|
Task
|
Responsibility
|
1.
|
✓
|
|
Publish the X.(Y+1)dev packages for download.moodle.org
|
Integration Lead
|