Major release process: Difference between revisions
From MoodleDocs
m (→Beta release) |
m (→Beta release) |
||
Line 26: | Line 26: | ||
# Clone MDL-28169 and MDL-28170, to be resolved ASAP. | # Clone MDL-28169 and MDL-28170, to be resolved ASAP. | ||
# More to clone... | # More to clone... | ||
# Prepare and publish the calendar for next Major release. | |||
==See also== | ==See also== |
Revision as of 00:00, 4 July 2011
Note: This page is a work-in-progress. Feedback and suggested improvements are welcome. Please join the discussion on moodle.org or use the page comments.
This page describes the standard procedures for making a major release e.g. Moodle 2.0.
Beta release
One month before:
- Freeze stable development and post in the General developer forum to inform everyone of the freeze
- Review and complete the release notes of the upcoming version.
- Test / QA etc
Release day:
- Verify all unit tests, QAs and integration tests pass!
- Run the mdlrelease process (with the special steps for Major releases).
- In Tracker, "release" the current version (with current date) and push any remaining open issues to the next point release (eg 2.1 -> 2.1.1) for developers to deal with there.
- Post about the release in the moodle.org news
Post release:
- Clone MDL-28169 and MDL-28170, to be resolved ASAP.
- More to clone...
- Prepare and publish the calendar for next Major release.