Major release process
From MoodleDocs
Note: This page is a work-in-progress. Feedback and suggested improvements are welcome. Please join the discussion on moodle.org or use the page comments.
This page describes the standard procedures for making a major release e.g. Moodle 2.0.
Beta release
One month before:
- Freeze stable development and post in the General developer forum to inform everyone of the freeze
- Review and complete the release notes of the upcoming version.
- Test / QA etc
Release day:
- In Tracker, "release" the current version (with current date) and push any remaining open issues to the next point release (eg 2.1 -> 2.1.1) for developers to deal with there.
- Post about the release in the moodle.org news