Line 444: | Line 444: | ||
* Update upcoming dates on the [[Roadmap]] page. | * Update upcoming dates on the [[Roadmap]] page. | ||
| [[#dev|Development Manager]] | | [[#dev|Development Manager]] | ||
|- | |||
| 13. | |||
| style="text-align:center" | ✓ | |||
| Upgrade all moodle.org and moodle.net sites to latest release version. | |||
| [[#sites|SITES team]] | |||
|} | |} | ||
Revision as of 07:41, 28 October 2013
Roles
Role | Person responsible |
---|---|
Lead Developer | Martin Dougiamas |
Integration Lead | Eloy Lafuente |
Community Manager | Helen Foster |
AMOS Maintainer | David Mudrák |
Moodle Docs Maintainer | David Mudrák |
Plugins Directory Maintainer | Aparup Banerjee |
Testing Maintainer | David Monllaó |
QA Master Site Maintainer | Helen Foster |
Digital Marketing Specialist | X.Y. Ng |
Development Manager | Michael de Raadt |
Updated 18 June 2013.
6 weeks prior
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | Create the next "X.Y+1" (next dev) version in the Tracker (MDL and CONTRIB), so people can move delayed stuff to next major release if needed. | Integration Lead | |
2. | ✓ | Freeze stable development and post in the General developer forum to inform everyone of the freeze. (example) | Development Manager | |
3. | ✓ | Create a "Must fix for 2.x" version in the tracker. | Development Manager | |
4. | ✓ | Check qa_test_required-labelled issues and create new QA tests as required. |
4 weeks prior
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | Start working on the release notes (template) of the upcoming version. | Development Manager | |
2. | ✓ | Release normal weeklies but with these changes in the master branch:
And make packages available under download.moodle.org (and windows). Promote master up in the download page and adjust info for it. |
Integration Lead | |
3. | ✓ | (Optionally) Announce Beta release in forums (ideally once packages are available). | Integration Lead | |
4. | ✓ | Review documentation for all issues with labels "dev_docs_required", removing this label when relevant docs are updated. | ||
5. | ✓ | During the QA weeks integration becomes continuous; release STABLE weeklies normally but master release as often as possible (or on demand). | Integration Lead | |
6. | ✓ | At some points produce release candidates (Z = 1, 2, 3..), which are normal builds with:
|
Integration Lead | |
7. | ✓ | Add a new version in the Plugins Directory with the beta version build number and the anticipated release version build number (https://moodle.org/plugins/admin/softwareversions.php). | Plugins Directory Maintainer | |
8. | ✓ | Tidy up current latest en version of Moodle Docs prior to copying it to create new version wiki as described in New docs version process. | ||
9. | ✓ | Prepare a fresh installation of the QA Master site based on the beta code to make sure the site is not affected by incremental upgrade steps during the development cycle. | QA Master Site Maintainer |
3 weeks prior
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | Create new QA test cycle and start QA testing. | Community Manager | |
2. | ✓ | Create new en and de Moodle Docs version wikis. | ||
3. | ✓ | ✓ | Check docs_required-labelled issues and write new documentation, removing the label and commenting in the issue when the work is done. | |
4. | ✓ | Go through all points listed under 3 weeks prior in New docs version process. |
1 week prior
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | Clone as many filters as needed in the Tracker, modifying them to point to the new, upcoming, branch (keeping same perms, title...). | Integration Lead | |
2. | ✓ | ✓ | Create new minor version X.Y.Z+1 in the Tracker (MDL and CONTRIB). Archive any version > 6 months old. | Integration Lead |
3. | ✓ | Clone MDL-39434 and bump all versions, requires and dependencies along all plugins in codebase to current date. | Integration Lead | |
4. | ✓ | ✓ | Post a "Heads-up" message on the Partners forum and General Developer forum. | Development Manager |
5. | ✓ | ✓ | Post a "Heads-up" message on Twitter and other outlets. | Digital Marketing Specialist |
6. | ✓ | ✓ | Merge fixes from en_fix pack and then integrate them. | AMOS Maintainer |
7. | ✓ | In https://github.com/moodlehq/moodle-behat-extension project:
|
Testing Maintainer | |
8. | ✓ | ✓ | Identify security issues that need to be integrated using the security_held label.
|
Integration Lead |
9. | ✓ | ✓ | Collect security issues into a clone of MDL-39530 to prepare for release of Security Advisories.
|
Development Manager |
10. | ✓ | ✓ | Review and complete the release notes for the upcoming minor versions.
|
Development Manager |
11. | ✓ | Check on the "Must fix for 2.x version". Filter out unrealistic issues. | Development Manager | |
12. | ✓ | Upgrade moodle.org (test server first, then production) | SITES team |
Day of release
Packaging
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | ✓ | Make sure there are no real blockers introduced in the last weekly (install / upgrade ...) | Integration Lead |
2. | ✓ | ✓ | Verify all unit tests and integration tests have passed. | Integration Lead |
3. | ✓ | Verify QA tests have passed. | Integration Lead | |
4. | ✓ | ✓ | Run the mdlrelease process, with the special steps for a Major release.
|
Integration Lead |
5. | ✓ | Create a new MOODLE_XY+1_STABLE branch in https://github.com/moodlehq/moodle-performance-comparison and set the new release commit hash as $basecommit | Testing Maintainer | |
6. | ✓ | ✓ | Wait for the automated moodle-package to finish building for all versions. Verify the process has ended successfuly (email). | Integration Lead |
7. | ✓ | ✓ | On the download server:
For major releases only:
|
Integration Lead |
8. | ✓ | ✓ | In the Tracker...
|
Integration Lead |
9. | ✓ | Create the new "Pull X.Y Branch" and "Pull X.Y Diff URL" custom fields and spread them to all the screens needing them (copy from previous ones). Reindex Tracker. Order them properly on each screen. Hide from all screens the custom fields belonging to 100% unsupported branches. | Integration Lead | |
10. | ✓ | ✓ | Add/update the release date, build number and link on the Releases page and date in new version pages. | Integration Lead |
11. | ✓ | ✓ | Post a "git repos updated & tagged" message on the Partner forum | Integration Lead |
Release
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | ✓ | The execution of "moodle-package-extract-and-postprocess X" script may be needed if the releases *are not going to be published on Monday* but another weekday (X is the weekday, (1-7) starting in Monday). | Integration Lead |
2. | ✓ | ✓ | Replace the download/index.php page with its updated counterpart. | Integration Lead |
3. | ✓ | ✓ | Replace the download/windows/index.php page with its updated counterpart. | Integration Lead |
4. | ✓ | ✓ | Notify all registered sys admins, including security notes with CVE identifiers. | Development Manager |
5. | ✓ | Post about the Major release on the moodle.org News forum | Lead Developer | |
6. | ✓ | Post about minor releases on the moodle.org News forum | Development Manager | |
7. | ✓ | ✓ | Post about the release on Twitter and other outlets. | Digital Marketing Specialist |
8. | ✓ | AMOS needs new "X.Y+1dev" branch to be created, to have master changes performed there. | AMOS Maintainer | |
9. | ✓ | Clone MDL-39753 and MDL-39754, to be resolved ASAP. | Integration Lead | |
10. | ✓ | ✓ | Verify, 24h after tagging, that https://moodle.org/dev/ has been updated with new versions. | Integration Lead |
11. | ✓ | Update Moodledocs default redirect and add version link to https://docs.moodle.org/overview/ | Moodle Docs Maintainer | |
12. | ✓ |
|
Development Manager | |
13. | ✓ | Upgrade all moodle.org and moodle.net sites to latest release version. | SITES team |
1 week after
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | ✓ | Publish the X.Y+ packages for download.moodle.org (should be automatic once weeklies are packaged). | Integration Lead |
2. | ✓ | ✓ | Update the version.php in git to be X.Y.Z+ during the next weekly integration process | Integration Lead |
3. | ✓ | ✓ | Create a new release notes page for the next minor versions (using the release notes template.) | Development Manager |
4. | ✓ | ✓ | Add all security advisories to Security news and release notes with links to security advisories | Development Manager |
5. | ✓ | ✓ | Send a plain text email to the OSS mailing list: oss-security@lists.openwall.com. An appropriate message when sending the issues is...
...followed by the security notes. |
Development Manager |
1 month after
# | Major | Minor | Task | Responsibility |
---|---|---|---|---|
1. | ✓ | Publish the X.(Y+1)dev packages for download.moodle.org | Integration Lead |
See also
- Major release process (deprecated)
- Release process (deprecated)
- Deprecation process (not deprecated)